The tank arrived from the factory with five fittings on top and one 1 1/4” drain plug on the bottom. The top connections were of various sizes....... 1 1/4”, 1”, 1”, 3/4” and 3/4”. I added three 1 1/2” Weldolets to the top of the tank and capped off both of the 3/4” inlets.
What you are seeing in the photo’s from left to right are
1 1/4” inlet (feed from boiler main loop)
1 1/2” add on ( 12"galvanized pipe nipple with 18” long reach thermometer monitoring tank temps)
1 1/2” add on ( 8"black pipe nipple with psi gauge)
1” supply line from tank to house baseboards and DHW indirect (house loop -draws hot water from top of tank)
3/4” capped off (this is the line tipping back towards the wall)
1” return from house loop (returns water to bottom of tank)
1 1/2” inlet add on (feed from boiler main loop)
3/4” capped off
We might have gotten by without adding the additional tank fittings but figured this way I will be covered if another zone or more gauges are needed. We have a 1000 sq ft shop attached to this garage that will likely get tied in also. The boiler return comes from the 1 1/4” line at the bottom of the tank.