I DO NOT WORK FOR MAINE ENERGY SYSTEMS!
The following is new information from Maine energy systems, but I think I beat the press release.
- The first shipment of boilers (~100) is slated to arrive late june/early july. Their first shipment is going exclusively to preorders; that is to say, they have no extra stock to sell until the next shipment.
- The entire system is now UL certified, even for apartment buildings.
- MEsys is working on a Journeyman license for solid fuels (journeyman licenses let installers work with indirect supervision, so a master solid fuel guy doesn't have to be on site while the non-master installer works)
- They have supplies of bulk pellets in July.
- Delivery trucks are being made at the factory.
- Deliveries of bulk pellets begin in 60 +/- 5 days.
The following is new information from Maine energy systems, but I think I beat the press release.
- The first shipment of boilers (~100) is slated to arrive late june/early july. Their first shipment is going exclusively to preorders; that is to say, they have no extra stock to sell until the next shipment.
- The entire system is now UL certified, even for apartment buildings.
- MEsys is working on a Journeyman license for solid fuels (journeyman licenses let installers work with indirect supervision, so a master solid fuel guy doesn't have to be on site while the non-master installer works)
- They have supplies of bulk pellets in July.
- Delivery trucks are being made at the factory.
- Deliveries of bulk pellets begin in 60 +/- 5 days.