Hi everyone, I am so glad to have found this forum, I have been reading it like crazy.
We are building a small new house this spring and have decided to add a wood stove, I think I want to go with the Englander vl-17 if I can still get my hands on one. We would also like to do a DIY install.
It is a vaulted ceiling with scissor trusses and the stove would go straight in the middle, so we would probably need to build down a little framed box for it to have a flat surface to enter through. Ideally I would like to go straight up through the roof peak, but will need to see if our builder thinks that is a good idea. Otherwise a 15 degree bend in the ‘attic’ space wouldn’t bother me too much.
I’ve been researching everything I can find but have a couple questions for those of you who are experienced.
What stage of construction should we install the chimney? My husband thinks it would be best to do it before the drywall goes up, which makes sense to me since there isn’t really an attic to get to from above due to the scissor trusses. My only question is, doesn’t the ceiling support box need to be installed on top of the drywall? Or maybe I am thinking about this wrong, tell me what I need to know.
Either way, I would like to not install the pipe or stove or hearth until all the painting etc has been done so they don’t get in the way.
I’ve attached a picture of the plans of the wall it will go on. Right in the middle of the room, against the wall as close as we can.
Thoughts! Thank you!
We are building a small new house this spring and have decided to add a wood stove, I think I want to go with the Englander vl-17 if I can still get my hands on one. We would also like to do a DIY install.
It is a vaulted ceiling with scissor trusses and the stove would go straight in the middle, so we would probably need to build down a little framed box for it to have a flat surface to enter through. Ideally I would like to go straight up through the roof peak, but will need to see if our builder thinks that is a good idea. Otherwise a 15 degree bend in the ‘attic’ space wouldn’t bother me too much.
I’ve been researching everything I can find but have a couple questions for those of you who are experienced.
What stage of construction should we install the chimney? My husband thinks it would be best to do it before the drywall goes up, which makes sense to me since there isn’t really an attic to get to from above due to the scissor trusses. My only question is, doesn’t the ceiling support box need to be installed on top of the drywall? Or maybe I am thinking about this wrong, tell me what I need to know.
Either way, I would like to not install the pipe or stove or hearth until all the painting etc has been done so they don’t get in the way.
I’ve attached a picture of the plans of the wall it will go on. Right in the middle of the room, against the wall as close as we can.
Thoughts! Thank you!