Eric Johnson said:
I can make as much headroom as I like with a shovel, but I like the concrete-over-insulation board idea. If I put 2 inches of good foam board down on top of a tamped gravel base, how many inches of concrete should I put down? Any need for stress relief in the slab?
You should have a vapor barrier, too. Barrier, then insulation, then concrete. Make sure the vapor barrier is good quality, and preferably use a couple layers, as you don't want ground water sapping heat away from the slab.
As nofossil mentions, you definitely want to use the edge barrier, as well (typically, more foam that is installed as part of the form, which simply stays when the slab is done). Dig a trench around the edge, allowing the foam to extend down vertically into the ground.
Eric Johnson said:
And as I understand Joe, you put the pex in place and pour the concrete over it?
Typically, the pex is zip-tied to the wire reinforcing grid. If not, it will float.
For a greenhouse, we typically use 1/2" tubing, 6" on-center. You'll not that the bend radius would prevent that, which we solve by alternating at one end. In other words, if the mechanical layout of the rows is 1-2-3-4-5-6, the actual tubing will go down row 1 then up row 4, then down row 2, then up row 5, then down row 3, then up row 6. That eliminated risks of kinking the tubing (even if you have it set up perfectly, the flow of the concrete might push it too far), and helps to reduce any temperature gradient across the floor.
As I've also mentioned, you can case tubing into raised planting beds/tables if you want. Warm-rooted plants don't mind cooler air temp, and that saves fuel by reducing heat loss through the glass.
As far as the thickness and type of concrete, I'd suggest talking to someone with experience pouring slabs. I just tie the tubing to their reinforcing grid, then stand back and let them work. I've never seen stress relief used in a radiant slab, though, and I expect it would need some precautions to prevent tube-shearing, if it were mechanically necessary.
Regarding the "mass," radiant works best as either a high-mass (concrete) or low-mass (Warmboard, etc.) system. The first works best when the whole system is high-mass (eg, with a storage tank), and is sometimes even set up for continuous circulation, with hot water injected into the loop on an as-needed basis. The low-mass radiant allows for quicker response, if you want to turn the temp down and them back up. Re-heating a slab wastes energy, so it's best to keep those sort of installations at a constant temp.
Joe